May 18, 2015

    • May 20, 2015

      The landscaping is completed. Villa Stefania is ready for the summer season 2015!

    • April 2, 2015

      The bower is installed at the territory.

    • March 24, 2015

      Completed installation of the fountain and benches in the area.

    • March 23, 2015

      The parking is finished. Each parking place now has its own interlock.

    • October 20, 2014

      Installation of fencing the area is completed. Entrance gate is installed.

    • May 19, 2014

      Commissioning. ACT 16 was received.

    • March 24, 2014

      Decorative furnishing works of facades are completed.

    • March 9, 2014

      Walls painting works in the studio Luciana are completed.

    • February 15, 2014

      Plastering and putty works in apartments Luciana, Brigida and Antonietta are completed.

    • January 5, 2014

      Finishing works in common areas are completed.

    • December 27, 2013

      Walls painting in common areas are completed.

    • December 10, 2013

      Laying tiles on the floors in the common areas are completed.

    • December 2, 2013

      Finishing works of the apartment Carmela and Ornella are completed.

    • November 29, 2013

      Plastering and putty works in the common areas are completed.

    • November 18, 2013

      Finishing works of apartments of the 2nd floor are completed.

    • September 5, 2013

      Finishing works of common areas of the 1st floor are completed.

    • August 23, 2013

      Finishing works of apartments of the 1st floor are completed.

    • June 25, 2013

      Wooden fences of terraces installation is completed.

    • May 29, 2013

      ACT 14.

    • May 24, 2013

      Start of the wooden fences of terraces installation.

    • May 23, 2013

      Plastering and painting works of facades are completed.

    • May 20, 2013

      Plaster works of apartments and common areas are started.

    • May 6, 2013

      Facades finishing works started

    • May 3, 2013

      Window and door installation started.

    • May 1, 2013

      Connection to external engineering networks is completed.

    • April 24, 2013

      Roof works are completed.

    • April 15, 2013

      Internal electric systems installation are complete.

    • April 6, 2013

      Start of roof construction works.

    • April 5, 2013

      Concrete operations on the 4th floor are complete.

    • April 2, 2013

      Masonry works on the 4th floor are complete.

    • March 28, 2013

      Internal engineering system installation on the 2nd floor are complete.

    • March 19, 2013

      Concrete operations on the 3rd floor are complete.

    • March 15, 2013

      Internal engineering system installation started.

    • March 11, 2013

      Masonry works on the 3rd floor are complete.

    • March 5, 2013

      Concrete operations on the 2nd floor are complete.

    • February 25, 2013

      Masonry works on the 2st floor are complete.

    • February 9, 2013

      Concrete operations and masonry works on the 1st floor are complete.

    • January 11, 2013

      Initial construction works are complete.

    • November 17, 2012

      Start of construction works. Foundation pit excavation.

    • October 9, 2012

      The permit for complex construction is granted.